DREDGING SET TO
BEGIN AT LAKE ILLAWARRA
January
30, 2007
The
long-awaited Lake Illawarra entrance dredging works will begin in
mid-February, restoring the amenity of nearby beaches and protecting up to
50 homes from the effects of ocean storms, Minister for the Illawarra
David Campbell said today.
Mr Campbell said as
part of the project up to 200,000 cubic metres of sand would be dredged
from Lake Illawarra’s entrance channel and used to nourish Warilla Beach.
“Over the coming
weeks the public will see Neumann Contractors moving their equipment and
materials to the site in preparation to start work,” Mr Campbell said.
“The local community
has waited a long time for this project to come to fruition and I am
pleased to see that the final stage is ready to start.
“The Iemma
Government, together with the two local councils, is committed to this
$5.75 million project which includes dredging the lake entrance and
constructing the two breakwaters.
“The first step will
be laying the pipeline to discharge dredged sand to the southern end of
Warilla Beach and should take around two weeks, then the actual dredging
process can begin.
Wollongong MP Noreen
Hay said along the pipeline route there were seven beach walkways to
cross but at each crossing the pipe would be buried so that public access
to the beach is not disrupted.
Labor candidate for
Shellharbour Lylea McMahon said the pipe would be laid along the existing
southern training wall, submerged under the swimming lagoon area, and then
laid across the beach to the eastern end car park off Reddall Parade,
along the reserve off Osborne Parade and Little Lake Crescent.
“Because of the
distance between the entrance channel and Warilla Beach a booster pump
will be initially installed on the southern training wall and the area
fenced off to protect the public during dredge operations,” Ms McMahon
said.
“The
dredge will be assembled on a small section of Reddall Reserve adjacent to
the Ocean Street boat ramp. After the dredge is assembled, a large crane
will lift the dredge into the waterway.”
Ms
Hay said this work should take about 2 weeks. During the launching of the
dredge, a section of the Ocean Street car park will be closed to the
public. …/2
“Dredging will proceed
upstream toward Berageree Island and when this section is completed
dredging will then proceed downstream toward the mouth,” Ms Hay said.
“During dredge
operations and discharge of sand to the beach, public access will be
restricted for safety reasons.”
Warilla Beach has
suffered from the effects of past sand mining and coastal erosion over
many decades, with an estimated 800,000 cubic metres of sand having been
lost since the 1940s.
“The resulting sand
nourishment of Warilla Beach will not only restore beach amenity but
provide an additional buffer to protect nearby houses from the effects of
severe ocean storms,” Ms Hay said.
“Work on the
breakwater structures has also recommenced after the Christmas break.
“The southern
breakwater is complete and about 100m of the northern breakwater remains
to be finished.”
All work should be
completed by about August 2007.